Scope of work
Bellevue Parks is proposing maintenance work on the pier and existing bulkhead to improve water quality, reduce erosion, and restore the structural capacity of the existing pier and bulkhead at Newcastle Beach Park. This work is considered a short-term solution while a longer term, soft bank solution is designed and constructed. The Newcastle Beach Park pier and bulkhead maintenance project includes three main elements: 1. Necessary repair and maintenance of the pier and adjacent bulkhead based on a recent condition assessment (WSP 2023). 2. Installation of a floating string of shore protection floats underneath the existing pier. 3. Construction of a sheet pile cut-off wall in front of the existing concrete bulkhead. Several mitigation actions are included in the proposed maintenance work to compensate for unavoidable environmental impacts from project actions: 1. 20 cubic yards of habitat material (1-inch minus mix: 100% less than 1 inch, 85% less than 0.5 inch, and 40% less than 0.25 inch) will be placed as mitigation for unavoidable environmental impacts from project actions. 2. 26 willow (Salix spp.) or red osier dogwood (Cornus sericea) live stakes will be planted into the habitat material. 3. Approximately 23 creosote-treated piles will be removed to the north of the public beach area. 4. 324 square feet of a swim beach platform and 2 guide piles will be removed.
Permit timeline
- AppliedApr 23, 202655 days in review
- IssuedJun 17, 20264mo ago
- ExpiresJun 16, 2029in 972 days
Details
- Project type
- Commercial renovation
- Work class
- Nonresidential
- Sector
- Commercial
- Permit type
- Minor commercial project
- City
- Bellevue, WA
- ZIP code
- 98006
- Status
- Issued
- Permit no.
- 26 109140 BW